The "transition period" starts on July  1st, 2026 and finish on July 1stJune 30th, 2028.

By the end of the transition period, the only way to connect to WIPO DAS will be via the DAS Office Portal or via REST API V2.


CountryIP OfficeCurrent means of connectionProduction date for REST API V1Estimation for migrating to REST API V2Notes
USUSPTOREST API V122 September 20252026(1)
KRMOIPTDA

Starting analysis of API REST
CNCNIPATDA

(1)
EPEPOTDA

(1)
JPJPOTDA

(1)
IBWIPOREST API V1October 2024
(1)
DEDPMAREST API V1November 2024
(1)
EMEUIPOTDA

(1)
AUIP AustraliaREST API V1
28 February
July 2026July 2028Starting with exchange via REST API V1 and Office Portal.
ESOEPMSFTP
2026/2027Planning stage
GBUKIPOSFTPApril 2026 (*)
(1)
FRINPIOffice Portal BulkQ1 2027
(1)
NZIPONZSFTP

(1)
SEPRVSFTP

(1)
ILILPOSFTP
2027Project being developed to move directly to V2
NONIPOOffice Portal
2026Project being developed for moving the DAS exchange to a combination of the Office Portal and DAS REST API V2
Note

(*) estimated

(1) waiting for estimation of V2 PROD date